Newburyport Senior Community Center, Newburyport, MA
​

Scope

New building construction

New parking and landscaping

Project Data

Area: 16,000 SF
Budget: $5,100 K

Construction Schedule
Start: September, 2014
Completion: September, 2015

​
Photography: Andy Caulfield
Malden Senior Community Center, Malden, MA
​

Scope

Adaptive reuse of former church, classrooms and recreation hall

Limited new parking, added bocce court and ramped entry

Project Data

Area: 22,000 SF
Budget: $4,355 K

Construction Schedule
Start: September, 2006
Completion: September, 2009

Milford Senior Center​, Milford, MA

​

Scope

New building construction

New parking and landscaping

Project Data

Area: 40,200 s.f.
Budget: $3,500 k

Construction Schedule
Start: September, 2002
Completion: January, 2004

​

Click here to view our LEED certification document for this building.

Tewksbury Senior Center, Tewksbury, MA 
​

Scope

New building construction (16K s.f.)

Existing building renovation (8K s.f.)

New parking and landscaping

Project Data

Area: 24,000 s.f.
Budget: $5,000 k

Construction Schedule
Start: May, 2005
Completion: December, 2006

​
Photography: Andy Caulfield
Wakefield Senior Center
​Wakefield, MA

 

Scope

Renovation of an existing school building into a senior center

Bring the building up to code

New parking and landscaping

Project Data

Area: 26,000 s.f.
Budget: $2,000 k

Construction Schedule
Start: September, 2000
Completion: June, 2002

Saugus Senior Center, Saugus, MA
​

Scope

New building construction

New parking and landscaping

Project Data

Area: 17,000 s.f.
Budget: $2,050 k

Construction Schedule
Start: June, 1996

Completion: July, 1997

Everett Senior Center, Everett, MA
​

Scope

Renovation of an existing armory building into a senior center.

Project Data

Area: 26,000 s.f.
Budget: $2,000 k

Construction Schedule
Start: September, 2000
Completion: June, 2002

​
​
Groton Community Center, Groton, MA
​

Scope

Combined building renovation and addition.

Existing parking and new landscaping.

Project Data

Area: 20,000 s.f.
Budget: TBA

Study Schedule
Study completion: 2007

East Bridgewater Senior Center Study​, East Bridgewater, MA

 

Scope

New building construction

New parking and landscaping

Project Data

Area: 19,222 s.f.
Budget: $2,264 k

Study Schedule
Study completion: 2006

Arlington Senior Center​, Arlington, MA
​

Scope

Renovation to former Central School Building

Project Data

Area: 35,771 s.f.
Budget: $5,479 k

Study Schedule
Study completion: April, 2016

Georgetown Community Senior Center, Georgetown, MA​
​

Scope

Renovation to former School Building

Project Data

Area: 12,521 s.f.
Budget: $293,844 

Construction Schedule
Construction start date: 2016

Prototypical "Net-zero Energy” Senior Center
​

Scope

Entry to the Unbuilt Architecture Competition- a generic urban senior center that is energy efficient as to use a net zero energy to operate.

Project Data

Area: 14,000 s.f.
Budget: $5,000 k 

Study Schedule
Study completion: 2014